Construction of Stage A Network (West) commenced in January 2013. Stage A Network (West) will provide water and wastewater services for an initial 1,900 residents of Googong. Construction of this work has been awarded to Woden Constructions, who are based in Queanbeyan.
The work involves construction of:
- Interim reservoirs for recycled and potable water.
- A sewage pumping station.
- Mains pipework, including recycled water mains, to connect to the first of five neighbourhoods to be built.
- Connection to the stormwater management system.
This stage is due to be completed in December 2013.